Project site is located on the Stevens Institute of Technology campus between the Howe Center and Davis Hall
Two existing buildings on-site, Jacobus and Hayden, were demolished 2019
Existing fenced pair of tennis courts along the north edge of the building shall remain as will the service drive at the north edge of Davis
Proposed project includes more than 430,000 gsf of floor area of which 76,000 gsf is dedicated to the University Center on levels G, 1, and 2 including a mechanical mezzanine above level G and a service tunnel
The north and south towers are 21 and 19 stories respectively
The height of the taller north tower is 225 ft
The two towers are connected at levels 3 and 4 by an enclosed 2-story bridge housing residential amenity spaces
University Center and lower levels of the towers are clad with a combination of masonry and curtainwall
Service drive/amenity terrace is located at level G along the east side of the building and structured above the steep incline above Frank Sinatra Drive