About the Project
- The Stephen F. Austin Middle School addition and renovation was a two phase project
- In the first phase, three existing buildings on the site were connected to create a new three-story middle school
- The new middle school is 126,000 sf and provides space for 949 students
- The addition was constructed using structural steel framing supported on drilled piers
- Second phase of the project involved renovating the original 1930’s middle school into the new Bryan ISD Administration building
- Original school building had been renovated several times throughout the years using cast-in-place concrete and structural steel systems